Plant Overhaul

Foundry Furnace Plant Decommissioning & Scrap Salvage

A coordinated industrial clearance programme for heavy ferrous scrap, crane components and recoverable materials, planned around ongoing plant operations.

Heavy Automotive Engineering Project case study
Plant Overhaul illustration Circular recovery
Total Weight Cleared 42.85 Metric Tons
Financial Recovery ₹15,24,000.00
Turnaround Time 48 Hours
CO₂ Emissions Abated ~76.5 Tons CO₂e

Inside the recovery project

01

The operational challenge

An automotive casting foundry in Howrah needed to replace an obsolete 15-ton induction furnace line. The congested site contained cast-iron moulding flasks, heavy beams and copper armature cables. Conventional dealers proposed unclear lump-sum pricing and delayed settlement.

02

Planning & logistics

A six-member industrial rigging team was planned with appropriate cutting tools, hydraulic equipment, personal protective equipment and container transport. Night-shift operations were selected to minimize disruption to the adjacent production bay.

03

Weighment & documentation

Sorted steel and copper batches were weighed on electronic platform scales, with readings checked by the client’s inspector. Batch records and weigh slips were documented for reconciliation.

Key outcomes

Material recovery

Recoverable ferrous material was directed toward downstream recycling channels.

Transaction records

Weight records and settlement documentation were prepared for the client’s review.

Publication note: Project quantities, payment amounts and performance claims in the supplied examples require supporting records before being presented as independently verified results.